Contract value
£1.6m
Architect
Faulkner Browns
Main contractor
Jerram Falkus Construction Ltd
Consulting Engineer
Hoare Lea
Services

New Gas Supply
External Water Supply
Heating Installation
Domestic Hot and Cold-Water Services
Ventilation
Comfort Cooling
Automatic Controls Including Associated Wiring
Sanitaryware
Above Ground Soil and Waste
Pool Water Make Up Pump

Project overview

This project consisted of construction of a new 25 metre six lane swimming pool with automated moving floor, dance and fitness studios, wet and dry changing facilities, WC’s, stores, and offices wrapped around the existing sport Hall which was in use during the main construction of the pool buildings. During the school summer holiday, the Sports hall was also refurbished.

The project included a new basement plantroom housing the new ventilation plant for the pool hall, new gas fired boilers along with Combined heat and power units and domestic hot and cold-water plant. The building was heated with underfloor heating throughout the changing facilities and pool surrounds with radiant panels in the sports Hall, Natural ventilation units we installed in the sports hall for ventilation.

Dedicated VRF heating/ cooling systems were installed for the studios, fitness suite, staff office and server/ AV rooms.